Gantt chart of the project:
A description of the project timeline for the development of predictive formulas for nitrogen content in liquid metal with respect to the 24-month duration and implementation schedule of each work package is provided in the following text and tables below.

Timeschedule of the project:
Begining of the project: 01.09.2024
End of the project: 31.08.2026
Project work packages (WP):
Full details and actual project state of the project Analytical modelling of nitrogen content prediction in pig iron and molten steel during steelmaking process is available via Microsoft Lists.



Work package 1 (WP1)
Data collection and preprocessing
Begining of WP1 - M1
End of WP1 - M3

Objectives: Work package WP1 will focus on acquiring raw operational data from the real steel plant, taking molten pig iron and molten steel samples, and preprocessing the data package.



Work package 2 (WP2)
Data analysis and exploration
Begining of WP2 - M4
End of WP2 - M6

Objectives: WP2 will be dedicated to the analysis and exploration of the collected data. The work package will look at the dataset, identifying patterns, trends and correlations. Using statistical methods, analytical modelling and regression analysis, the project will gain a deeper insight into the data.



Work package 3 (WP3)
Model development
Begining of WP3 - M7
End of WP3 - M24

Objectives: WP3 is the core phase of the project. By combination of statistical modeling, econometric algorithms, and machine learning techniques nitrogen prediction models will be developed.



Work package 4 (WP4)
Model validation
Begining of WP4 - M19
End of WP4 - M24

Objectives: Validation of the proposed prediction models during WP4, to improve the accuracy and validate the predicted results. Accuracy testing on real data.



Work package 5 (WP5)
Dissemination and communication of results
Begining of WP5 - M7
End of WP5 - M24

Objectives: To maximize the impact of results and deliverables in the creation of prediction formulas, a comprehensive communication and dissemination strategy is essential. This WP5 deals extensively with the dissemination of the results achieved during the project in the form of scientific articles and reports.
List of project milestones:
Milestone
Work package (WP) number
Method of verification
Expected time to reach the milestone (project month)
Project website creation
WP1Availability checkM1
Setup of encrypted data storage NAS
WP1
Shareability checkM1
Final pre-processed and cleaned data set
WP1
Project websiteM3
Final processed data set
WP2
Project website
M6
Microsoft Azure cloud service creation
WP3
Pay-as-you-go invoice / Project websiteM7
Preparation of conference contribution
WP5
Proceedings / Project websiteM9
Preparation of scientific paper
WP5
Journal / Project websiteM11
First prediction model iteration available
WP3
Interim report / Project websiteM13
Preparation of scientific paper
WP5
Journal / Project websiteM14
Preparation of scientific paper
WP5
Journal / Project websiteM17
Preparation of conference contribution
WP5
Proceedings / Project website
M17
Preparation of scientific paper
WP5
Journal / Project websiteM21
Final prediction model achieved
WP3
Final report / Project websiteM24
List of project deliverables:
Deliverables
Work package (WP) number
Method of verification
Expected time to reach the milestone (project month)
Creation of project website
www.nitrogen-prediction.eu
WP1Availability checkM1
Scientific international conference
WP5
Proceedings / Project websiteM10
Scientific paper
WP5
Journal / Project website
M12
Interim report
WP5
Project website
M13
Scientific paper
WP5
Journal / Project website
M15
Scientific paper
WP5
Journal / Project website
M18
Scientific international conference
WP5
Proceedings / Project website
M18
Scientific paper
WP5
Journal / Project website
M22
Final report
WP5
Project websiteM24
Download section of deliverbles:
Scientific papers
  • Article 1 - Analysis of Factors Contributing to Crude Steel Nitridation in Basic Oxygen Furnace Prior to Tapping (Download PDF)
  • Article 2 - Download
  • Article 3 - Download
  • Article 4 - Download
  • Article 5 - Download
Project reports
  • INTERIM REPORT - Download
  • FINAL REPORT - Download